MyProjectCalcs

Concrete Slab Calculator

By Vinod Kondeti · Updated

A slab is the simplest pour there is: one flat rectangle. That's why it's also where a small measuring slip costs the most, because the slip is multiplied across the whole area. The calculator is set to a 12 × 12 ft pad, a common size for a garden shed base. Change it to your own size.

Cubic yards –

Weight in pounds (no waste added)–
Weight in US tons–
Weight in kilograms–
Cubic feet–
Cubic meters–
80 lb bags (0.60 ft³ each)–
60 lb bags (0.45 ft³ each)–
40 lb bags (0.30 ft³ each)–
80 lb bags per piece, if you mix each one on its own–
Cost in 80 lb bags–
Cost as ready-mix–

Working: –

Cost estimate (optional: enter your local prices)
lengthwidthdepth

Worked example: a 12 × 12 ft shed pad

  • Volume: 12 × 12 × (4 ÷ 12) = 48 ft³, which is 1.78 yd³ before waste.
  • With the 10% waste allowance: 52.8 ft³ = 1.96 yd³.
  • Bags: 52.8 ÷ 0.60 = 88 × 80 lb bags, or 118 × 60 lb, or 176 × 40 lb.

Eighty-eight bags is more than three tons of dry mix. At almost two yards, a 12 × 12 pad is usually a ready-mix job. Use the bag count to compare prices, not as a plan for mixing by hand.

What a thicker slab costs you

Every extra inch on this pad adds 12 ft³ before waste. At 6 in instead of 4 in, the same pad needs 2.93 yd³ (132 × 80 lb bags) with waste. That's 50% more concrete for 50% more thickness, because volume rises in direct proportion. Choose the thickness from your plans or the shed maker's instructions, not by rounding up "to be safe".

Measuring a slab that will actually match the calculator

  1. Measure inside the forms once they're staked. Measuring the excavation before the forms go in can be off by the board thickness on every side.
  2. Check the depth at the four corners and the middle. A string line pulled tight across the top of the forms makes this easy: measure down from the string to the base.
  3. Average the depth readings and enter that, not the target thickness. If the average is 4.5 in, enter 4.5. The thickness box takes inches; to convert a reading such as 4 3/8 in to feet for hand math, use the inches to decimal feet chart.
  4. Square the forms first. Measure both diagonals. If they match, the slab is rectangular and length × width is accurate.
  5. If the slab has steps up to a door, add them with the concrete step calculator.

Mistakes specific to slabs

  • Forgetting a thickened edge. Some slabs have a deeper perimeter. Calculate that strip separately with the footing calculator and add it.
  • Leaving out the base. The gravel base under a slab is a separate material. Estimate it with the gravel calculator.
  • Pouring in two sessions. A slab finished in two pours hours apart can leave a weak seam. QUIKRETE's data sheet warns against partial fills for this reason.
  • Skipping curing. QUIKRETE says to keep the surface moist for 5 days at 70 °F or above, or 7 days at 50–70 °F.
  • Forgetting the steel. Reinforcement is a separate order. If your plans call for rebar, work out how much rebar your slab needs in bars, feet and pounds. Not sure whether to use mesh or rebar? See rebar vs wire mesh for a slab.

Concrete per 100 ft² by thickness

Thickness Volume per 100 ft² Cubic yards 80 lb bags
3.5 in 29.17 ft³ 1.08 49
4 in 33.33 ft³ 1.23 56
5 in 41.67 ft³ 1.54 70
6 in 50.00 ft³ 1.85 84

No waste is included in this table. Scale it to your slab: a 200 ft² slab at 4 in is twice the row, 2.47 yd³.

Common slab sizes at 4 in

With 10% waste included:

Slab Volume Cubic yards 80 lb bags 60 lb bags
8 × 8 ft 23.47 ft³ 0.87 40 53
10 × 10 ft 36.67 ft³ 1.36 62 82
10 × 12 ft 44.00 ft³ 1.63 74 98
12 × 12 ft 52.80 ft³ 1.96 88 118
12 × 16 ft 70.40 ft³ 2.61 118 157
16 × 16 ft 93.87 ft³ 3.48 157 209
20 × 20 ft 146.67 ft³ 5.43 245 326

The 10 × 10 slab is worked through step by step in how many bags of concrete for a 10x10 slab.

Ordering ready-mix

One ready-mix supplier's ordering guide (R&R Ready Mix) asks customers to allow about 10% for an uneven subgrade and spillage, and to round up to the nearest ¼ yard. For the 12 × 12 pad, 1.96 yd³ rounds up to 2 yd³. The same guide says small loads may carry a partial-load charge, so ask your supplier for their minimum. It also warns against adding water on site to make the mix flow more.

Control joints

QUIKRETE's data sheet says to cut control joints 1 in deep every 6 to 8 ft in a slab. A 12 × 12 pad gets one joint each way through the middle, making four 6 × 6 ft panels. Joints don't change the volume.

Frequently asked questions

How many bags of concrete for a 12 × 12 slab?

At 4 in thick, 80 × 80 lb bags with no allowance (48 ÷ 0.60), or 88 with 10% for waste.

How many yards of concrete for a 12 × 12 slab at 6 inches?

72 ft³ = 2.67 yd³, or 2.93 yd³ with 10% waste.

Can I use this for an L-shaped slab?

Yes. Split the L into two rectangles, run each one, and add the totals.

How many bags of concrete per 100 square feet?

At 4 in thick, 33.33 ft³: 56 × 80 lb bags before waste.

How many yards for a 20 × 20 slab at 4 inches?

133.33 ft³ = 4.94 yd³ before waste, or 5.43 yd³ with 10%.

Sources

Bag yields: 0.30 / 0.45 / 0.60 ft³ for 40 / 60 / 80 lb standard concrete mix (manufacturer data sheets). The concrete guide has the formulas and worked examples. Questions about mixing water, curing time or bag yields? See the concrete FAQ.

Other concrete calculators

Related calculators