How to Calculate Yards of Concrete (L × W × D ÷ 27)

By Vinod Kondeti · Updated

To calculate yards of concrete, multiply length × width × depth, with every measurement in feet, then divide by 27. The answer is cubic yards, the unit ready-mix suppliers sell by. This guide shows how to figure out yards of concrete (your concrete yardage) step by step, with worked examples for a slab, a footing, a post or column, and a measurement taken in feet and inches. To skip the math, use the concrete calculator.

How to calculate yards of concrete in 4 steps

To figure yards of concrete for any square or rectangular pour:

  1. Measure length, width and depth. Measure inside the forms. Take the depth at each corner and in the middle and use the average, because ground that looks flat often isn't.
  2. Convert inches to feet. Divide inches by 12. A 4 in slab is 4 ÷ 12 = 0.333 ft.
  3. Multiply L × W × D to get cubic feet (ft³).
  4. Divide by 27 to get cubic yards (yd³). One cubic yard is 3 ft × 3 ft × 3 ft = 27 ft³.

Then add a waste allowance (10% is the usual default) and round up to what your supplier sells.

Cubic yards = length (ft) × width (ft) × depth (ft) ÷ 27

Converting inches to feet

Inches Feet
2 in 0.167 ft
3 in 0.25 ft
4 in 0.333 ft
5 in 0.417 ft
6 in 0.5 ft
8 in 0.667 ft
12 in 1 ft

Worked example: a measurement in feet and inches

A pad measures 12 ft 6 in × 10 ft and is 5 in deep.

  • 12 ft 6 in = 12 + 6 ÷ 12 = 12.5 ft. 5 in = 5 ÷ 12 = 0.417 ft.
  • 12.5 × 10 × 0.417 = 52.08 ft³.
  • 52.08 ÷ 27 = 1.93 yd³, or 2.12 yd³ with 10% waste.

Never multiply feet by inches. 12.5 × 10 × 5 gives 625, a number 12 times too large.

How many square feet does one yard of concrete cover?

One cubic yard of concrete covers 81 square feet at 4 inches thick. A cubic yard is 27 ft³, and 4 in is 1/3 ft, so 27 ÷ 1/3 = 81 ft², the same as a 9 × 9 ft pad. Thicker pours cover less: 64.8 ft² at 5 in (27 ÷ 5/12) and 54 ft² at 6 in (27 ÷ 1/2). To figure yardage from an area you already know, work backwards: divide the square footage by the coverage for your thickness. A 405 ft² patio at 4 in needs 405 ÷ 81 = 5 yd³ before waste. Other thicknesses are in the coverage table on concrete formulas.

Worked example: a slab

A 12 × 10 ft slab at 4 in thick:

  • 12 × 10 × 0.333 = 40 ft³.
  • 40 ÷ 27 = 1.48 yd³.
  • With 10% waste: 44 ft³ = 1.63 yd³.

If the slab needs steel, see rebar vs wire mesh for a concrete slab for which to use and how high it should sit. Weighing a thicker pour? 4 inch vs 6 inch concrete slab compares how much more concrete 6 in takes and when it's worth it.

Worked example: a footing

Footing sizes are usually given in inches. A 20 ft run of 16 in wide, 8 in deep footing:

  • Width 16 ÷ 12 = 1.333 ft. Depth 8 ÷ 12 = 0.667 ft.
  • 20 × 1.333 × 0.667 = 17.78 ft³.
  • 17.78 ÷ 27 = 0.66 yd³, or 0.72 yd³ with 10% waste.

For a whole foundation, measure along the centerline of the trench so the corners aren't counted twice.

Worked example: a post or column

A round post hole, pier or column is a cylinder, so L × W becomes the area of a circle: π × radius², where the radius is half the diameter in feet.

  • Round column or sonotube, 12 in across and 4 ft tall: radius 0.5 ft. 3.1416 × 0.5² × 4 = 3.14 ft³, which is 3.14 ÷ 27 = 0.12 yd³. Six of them with 10% waste is 20.73 ft³ = 0.77 yd³. See the sonotube calculator or the column calculator.
  • Square column, 12 × 12 in and 8 ft tall: it is a box, so L × W × D works directly. 1 × 1 × 8 = 8 ft³ = 0.30 yd³.
  • Fence post hole, 10 in across and 30 in deep around a 4×4 post (actual size 3.5 in): subtract the post. (3.1416 × 0.417² − 0.292²) × 2.5 = 1.15 ft³. See the post hole calculator.

Walls, steps and other shapes

The same method covers every shape: find the volume in cubic feet, then divide by 27. For the wall, step, metric and one-step ÷ 324 formulas in a single reference table, see concrete formulas. For irregular areas, split the shape into rectangles and circles, work out each one and add them.

From yards to bags

Bags = cubic feet ÷ bag yield, rounded up. A standard 80 lb bag yields 0.60 ft³, so the 40 ft³ slab above takes 67 bags before waste and 74 with 10%. The concrete bag calculator has bags per yard for 40, 60 and 80 lb mix. To calculate cement rather than premix, remember that portland cement is the binder in concrete: mixed with water, it forms the paste that binds the sand and gravel together. QUIKRETE's Portland Cement data sheet says five to six 94 lb bags are typically used per cubic yard, and the mix ratio calculator works out cement, sand and gravel for your volume.

Add a waste allowance

No pour uses exactly the calculated volume. Concrete gets spilled, forms bow slightly, the subgrade settles under the weight, and some is left in the mixer or wheelbarrow. The calculator adds 10% by default.

  • Use more (15% or above) for hand-dug holes, uneven or soft ground, or footings dug without forms.
  • Use less only for small, formed pours on a compacted, level base, such as a 10x8 shed base.

Running short is the expensive mistake. A second batch mixed hours later can leave a cold joint, a visible seam that may be weaker than continuous concrete. QUIKRETE's data sheet warns against partial-depth fills for this reason.

Ordering: bags or ready-mix?

Weight decides this as much as cost. One cubic yard is 45 × 80 lb bags: 3,600 lb to carry and mix, plus water.

Job size Usual approach
A few posts, a small pad, under ~0.5 yd³ Bags, mixed in a wheelbarrow or tub
~0.5 to 1 yd³ Bags with a rented mixer, or a small-load supplier
Over ~1 yd³ Ready-mix truck

These breakpoints are rules of thumb, not prices. Ready-mix suppliers often have a minimum load and may charge a fee for small loads. Call two local suppliers with your cubic yard figure and compare the delivered total against the bag count × bag price.

When you order ready-mix, tell the supplier:

  • the volume in cubic yards, including waste;
  • what you're pouring (slab, footing, wall), so they can suggest a mix;
  • how the truck will reach the pour, and whether you need a pump or a wheelbarrow crew.

Mixing bagged concrete correctly

QUIKRETE's data sheet calls for about 6 pints of water per 80 lb bag to start. The final water content should be about 6 to 9 pints, added gradually until the mix is stiff and moldable, with no dry pockets and no standing puddles.

  • Mixer size: allow at least 1 ft³ of mixer capacity for each 80 lb bag mixed at one time.
  • Don't add too much water. Extra water makes concrete easier to place but weaker.
  • Mix fully: check for dry pockets at the bottom of the tub.

Curing: the step most people skip

Curing keeps moisture in the concrete so the cement keeps hydrating and gaining strength. The American Cement Association (formerly the Portland Cement Association) says to start curing once the surface has hardened enough to resist marring. You can cure by:

  • sprinkling, fogging, or covering with wet burlap or cotton mats;
  • sealing in moisture with plastic sheeting or a curing compound.

QUIKRETE's data sheet says to continue curing for 5 days in warm weather (70 °F or higher) or 7 days in colder weather (50–70 °F). The same sheet lists compressive strength of about 2,500 psi at 7 days and 4,000 psi at 28 days for its Concrete Mix. Concrete keeps gaining strength well after it looks dry.

Common mistakes

  1. Mixing units. Multiplying feet by inches gives a number 12 times too large.
  2. Using nominal lumber sizes. Form boards and posts are smaller than their names.
  3. Measuring thickness once. Average several readings.
  4. Forgetting the post. Without subtracting it, a post hole estimate runs high. That's harmless, but it overstates cost.
  5. No waste allowance. Plan for leftovers, not a shortfall.
  6. Pouring in the wrong weather. Very hot, dry, windy or near-freezing conditions all make curing harder. Check the forecast.

Frequently asked questions

Why do you divide by 27 to get yards of concrete?

A cubic yard is 3 ft long, 3 ft wide and 3 ft deep, so it holds 3 × 3 × 3 = 27 ft³. Dividing cubic feet by 27 converts them to cubic yards.

How do I convert inches to feet for concrete?

Divide inches by 12 before you multiply. 4 in is 0.333 ft, 6 in is 0.5 ft, and 12 ft 6 in is 12.5 ft. For fractions of an inch, use the inches to decimal feet chart.

What if the depth varies across the pour?

Measure the depth in several places, at each corner and in the middle, and use the average. A 4 in slab that averages 4.5 in needs 12.5% more concrete.

Do I need to subtract rebar or mesh?

No. Reinforcement takes up a negligible share of the volume.

Sources

Calculators for specific jobs

Open the concrete calculator →