MyProjectCalcs

How Much Concrete for a 10x8 Shed Base? (Bags & Yards)

By Vinod Kondeti · Published

A 10 × 8 ft shed base poured 4 inches thick holds 26.67 cubic feet of concrete, which is 0.99 cubic yards. In bagged mix that’s 45 bags of 80 lb, 60 bags of 60 lb or 89 bags of 40 lb, with nothing to spare. Add a 10% allowance for an uneven base and spills and you should buy 49 × 80 lb bags (66 × 60 lb, or 98 × 40 lb), which is about 1.09 yd³.

The rest of this post shows where those numbers come from, how thickness and shed size change the count, and the gravel base under the pour. To run your own size, use the concrete slab calculator. For a square pad, see how many bags of concrete for a 10x10 slab.

The math for a 10 × 8 shed base at 4 inches

Concrete is sold by volume, so start with length × width × thickness, with every measurement in feet.

  1. Area: 10 ft × 8 ft = 80 ft².
  2. Volume: 80 ft² × (4 ÷ 12) ft = 26.67 ft³.
  3. Cubic yards: 26.67 ÷ 27 = 0.99 yd³ (about 0.76 m³, since a foot is exactly 0.3048 m).
  4. Bags: divide the cubic feet by what one bag makes. QUIKRETE’s Concrete Mix data sheet lists about 0.60 ft³ for an 80 lb bag, 0.45 ft³ for 60 lb and 0.30 ft³ for 40 lb. SAKRETE’s data sheet for its High-Strength mix gives the same yields.
    • 80 lb: 26.67 ÷ 0.60 = 44.4, so 45 bags.
    • 60 lb: 26.67 ÷ 0.45 = 59.3, so 60 bags.
    • 40 lb: 26.67 ÷ 0.30 = 88.9, so 89 bags.
  5. Add the allowance: 26.67 × 1.10 = 29.33 ft³ (1.09 yd³). That gives 49, 66 and 98 bags.

Always round bags up. A bag short at the end of a pour is a real problem, because QUIKRETE’s data sheet tells you to fill the form to full depth and avoid partial fills, which can leave cold joints.

A quick check against SAKRETE’s shortcut

SAKRETE’s guide to estimating bagged jobs gives a shortcut for 4 inch slabs: multiply the square footage by 0.6 to get the number of 80 lb bags, with roughly 10% extra built in. For 80 ft², that’s 48 bags. Our exact figure is 44.4 bags before the allowance, so the shortcut adds about 8%, and 49 bags adds a full 10%. Either one gets you close. The same guide says 45 bags of 80 lb mix make a cubic yard, and a yard at 4 inches covers 81 ft². Both match the arithmetic above (80 ÷ 81 = 0.99 yd³).

How thickness changes the count

Volume rises in step with thickness, so a 6 inch slab needs 50% more concrete than a 4 inch one. QUIKRETE’s guide to sidewalks and small slabs says simple slabs for small foundations and bases are normally 4 to 6 inches thick, depending on the load they have to carry. Use the thickness from your plans or your shed maker’s instructions.

Thickness Volume with 10% Cubic yards 80 lb bags 60 lb bags 40 lb bags
4 in 29.33 ft³ 1.09 49 66 98
5 in 36.67 ft³ 1.36 62 82 123
6 in 44.00 ft³ 1.63 74 98 147

Without the allowance, the same 10 × 8 pad is 0.99 yd³ at 4 inches (45 × 80 lb), 1.23 yd³ at 5 inches (56 × 80 lb), and 1.48 yd³ at 6 inches (67 × 80 lb).

A 2 × 4 is 3½ inches wide, and QUIKRETE’s patio instructions say to allow 3½ inches for the concrete when you use 2 × 4 forms. If you’re planning a “4 inch” slab in 2 × 4 forms, measure from the top of the forms down to the compacted base, average the readings, and enter that depth in the slab calculator.

Common shed sizes at 4, 5 and 6 inches

Every row includes the 10% allowance. Cubic yards and 80 lb bags are shown at 4, 5 and 6 inches; for 60 or 40 lb bags, use the bag calculator or divide cubic feet by 0.45 or 0.30 and round up.

Slab Area 4 in yd³ 4 in 80 lb 5 in yd³ 5 in 80 lb 6 in yd³ 6 in 80 lb
6 × 4 ft 24 ft² 0.33 15 0.41 19 0.49 22
8 × 6 ft 48 ft² 0.65 30 0.81 37 0.98 44
10 × 8 ft 80 ft² 1.09 49 1.36 62 1.63 74
10 × 10 ft 100 ft² 1.36 62 1.70 77 2.04 92
10 × 12 ft 120 ft² 1.63 74 2.04 92 2.44 110
12 × 16 ft 192 ft² 2.61 118 3.26 147 3.91 176

As a cross-check, SAKRETE answered a reader’s question about an 8 × 15 ft shed slab at 4 inches with 74 × 80 lb bags. The same formula gives 8 × 15 × (4 ÷ 12) × 1.10 = 44 ft³, and 44 ÷ 0.60 = 73.3, which rounds up to 74. For an L-shaped pad, split it into rectangles with the square footage calculator before multiplying by thickness.

Slab overhang beyond the shed footprint

The figures above are for the slab itself. Many shed pads are poured a little larger than the shed footprint so the walls sit inside the concrete and rainwater sheds off the edge rather than under the sill. If your shed is 10 × 8 and your plans call for a 6 inch overhang on every side, the pour becomes 11 × 9 ft. At 4 inches with 10% extra that is 11 × 9 × (4 ÷ 12) × 1.10 = 36.30 ft³, or 1.34 yd³ — 61 × 80 lb bags (81 × 60 lb, or 121 × 40 lb). Enter the larger length and width in the calculator rather than the shed’s nominal size.

Bags versus ready-mix

At about 1.09 yd³ with the allowance, a 10 × 8 pad sits near the line where bagging and a small ready-mix order both make sense.

  • Weight: 49 × 80 lb is 3,920 lb of dry mix, almost two tons. Smaller bags don’t make it lighter overall — you just lift more of them.
  • Water: QUIKRETE’s data sheet puts the final water content at about 6 to 9 pints per 80 lb bag (roughly 37 to 55 gallons for 49 bags) and at least 1 ft³ of mixer capacity per 80 lb bag in a batch.
  • Ready-mix minimum: many plants sell by the cubic yard and set a minimum load (often around a yard, sometimes more, plus a short-load fee). Ask your local supplier before you decide. The concrete bag calculator turns a yardage figure into bag counts, and both calculators take optional local prices so you can compare bags with a delivered load.

The gravel base under a 10 × 8 shed slab

Concrete usually sits on a compacted gravel base, and that’s a separate purchase. QUIKRETE’s slab instructions call for 3 to 4 inches of gravel, tamped down. Its patio instructions are more specific: spread about 5 inches of compactible gravel and tamp it to 4, and extend the base at least 6 inches past the slab on every side.

For a 10 × 8 slab, that makes the gravel footprint 11 × 9 ft. At 4 inches compacted, that’s 99 ft² × (4 ÷ 12) = 33.00 ft³, or 1.22 yd³. With the gravel calculator’s default 10% extra, it comes to 36.30 ft³, or about 1.34 yd³. If you follow the patio method and spread 5 inches before tamping, the loose volume is 41.25 ft³ (1.53 yd³), or 45.38 ft³ (1.68 yd³) with 10% extra. Gravel is sold by weight as well as volume, so ask your supplier how much their product weighs per cubic yard.

Frequently asked questions

How much concrete for a 10x8 shed base at 4 inches?

0.99 cubic yards with nothing extra, or 1.09 yd³ with a 10% allowance. That is 45 × 80 lb bags, or 49 with the allowance.

How many 80 lb bags of concrete for a 10x8 slab?

At 4 inches thick, 45 bags exactly, or 49 with 10% extra. At 6 inches it’s 67 bags, or 74 with the allowance.

How many 60 lb bags for a 10x8 shed slab?

60 bags at 4 inches with nothing extra, or 66 with 10% extra (about 0.45 ft³ per bag).

Should the slab be larger than the shed?

Often yes — a small overhang past the walls helps water shed away from the sill. Size the pour to your plans (for example 11 × 9 with 6 inches on each side), then run those dimensions through the slab calculator.

Bags or ready-mix for a 10x8 shed base?

It depends on local bag prices, the ready-mix minimum load, and any delivery fee. Enter both prices in the slab calculator to compare.

How much gravel under a 10x8 shed slab?

With a base 6 inches past each edge and 4 inches deep after tamping, about 1.22 yd³, or 1.34 with 10% extra. At 5 inches loose before tamping, about 1.53 yd³, or 1.68 with the allowance.

Sources

Tags: concrete, sheds, slabs