Getting the total run right
Footing estimates go wrong at the corners. If you add up the four outside dimensions of a building, each corner block gets counted twice. Use the centerline instead: measure along the middle of the footing trench all the way round.
For a rectangular building, the centerline length is roughly the outside perimeter minus 4 × the footing width. For estimating, the simpler habit is to measure two opposite sides full length and the other two between them.
Worked example: a 12 × 16 ft garage-style footing
- Centerline run: 2 × (12 + 16) = 56 ft. That treats the dimensions as centerline measurements.
- Volume: 56 × (16 ÷ 12) × (8 ÷ 12) = 49.78 ft³ = 1.84 yd³.
- With 10% waste: 54.76 ft³ = 2.03 yd³, or 92 × 80 lb bags.
If the plans call for a bigger footing
At 20 in wide and 10 in deep, the same 56 ft run needs 3.17 yd³ with waste, more than 50% extra. Width and depth multiply each other, so a modest change in both adds up quickly. Footing size, depth below grade and reinforcement come from your plans and local building department (footings typically take rebar rather than mesh; see rebar vs wire mesh). This tool only does the volume math. For deck footings, see how deep deck footings should be for the code rule and frost-depth examples.
Mixed-size runs: adding sections together
Many foundations don't use one footing size all the way round. A bearing wall in the middle of a house may sit on a wider footing than the outside walls, and a porch or post may need its own pad. Work out each size as its own section, add the volumes, and only then round to bags.
Example: 40 ft of 20 × 10 in footing under a bearing wall, plus the 56 ft run of 16 × 8 in from the garage example.
- 20 × 10 in section: 40 × (20 ÷ 12) × (10 ÷ 12) = 55.56 ft³.
- 16 × 8 in section: 56 × (16 ÷ 12) × (8 ÷ 12) = 49.78 ft³.
- Combined: 105.33 ft³ before waste, or 115.87 ft³ (4.29 yd³) with 10% waste.
- Bags: 115.87 ÷ 0.60 = 193.1, so 194 × 80 lb bags. QUIKRETE rates an 80 lb bag of Concrete Mix at about 0.60 ft³.
To do this here, run the calculator once for each section with the same waste setting and add up the cubic feet it shows. Adding cubic feet first and dividing by the bag yield once gives the smallest honest bag count. Rounding each section to whole bags and then adding can come out a bag or two higher.
Bag rounding: whole bags, and pieces mixed one at a time
Bags only come whole, so the count is always rounded up. 193.1 bags means buying 194, never 193.
Rounding up also matters when separate pieces are mixed and poured one at a time. Add two 24 × 24 × 12 in pads to the example above. With 10% waste they hold 4.4 ft³ each, or 8.8 ft³ together:
- Mixed as one batch, 8.8 ÷ 0.60 = 14.7, so 15 × 80 lb bags.
- Mixed one pad at a time, each pad needs 4.4 ÷ 0.60 = 7.3, so 8 bags per pad and 16 bags for the pair.
On the whole job (both strip sections plus the two pads), that's 124.67 ft³ (4.62 yd³) and 208 × 80 lb bags if it is all counted together, or 194 + 16 = 210 bags if each pad is mixed on its own. When you set a quantity above 1, the calculator shows the per-piece bag count, so you can buy for the way you'll actually mix. At these totals, more than 4 yd³, ready-mix is usually the practical choice anyway, and the cubic yards are the number to give the supplier.
Concrete per foot of footing
Volume for common footing sizes, before waste. Use it to check your result or to price a run quickly.
| Footing (width × depth) | ft³ per ft | yd³ per 10 ft | yd³ per 100 ft | 80 lb bags per 10 ft |
|---|---|---|---|---|
| 12 × 6 in | 0.50 | 0.19 | 1.85 | 9 |
| 12 × 8 in | 0.67 | 0.25 | 2.47 | 12 |
| 16 × 8 in | 0.89 | 0.33 | 3.29 | 15 |
| 16 × 10 in | 1.11 | 0.41 | 4.12 | 19 |
| 20 × 8 in | 1.11 | 0.41 | 4.12 | 19 |
| 20 × 10 in | 1.39 | 0.51 | 5.14 | 24 |
| 24 × 12 in | 2.00 | 0.74 | 7.41 | 34 |
These are sizes people often ask about, not recommendations. Your plans set the size.
Pad footings (square pads)
A pad footing is a single square or round block under a post, pier or column, rather than a long strip under a wall. If the column above the pad is concrete too, size it with the concrete column calculator and add the two totals. This calculator handles square pads too:
- Set the footing length to the side of the pad in feet. A 24 in pad is 2 ft.
- Set the width to the same side in inches (24) and the depth in inches.
- Set the quantity to the number of identical pads.
| Pad | ft³ each | 80 lb bags each | 60 lb bags each |
|---|---|---|---|
| 16 × 16 × 8 in | 1.19 | 2 | 3 |
| 18 × 18 × 8 in | 1.50 | 3 | 4 |
| 20 × 20 × 10 in | 2.31 | 4 | 6 |
| 24 × 24 × 10 in | 3.33 | 6 | 8 |
| 24 × 24 × 12 in | 4.00 | 7 | 9 |
| 30 × 30 × 12 in | 6.25 | 11 | 14 |
Example: eight 24 × 24 × 12 in pads. 2 × 2 × 1 = 4.00 ft³ each, 32 ft³ in total, or 35.20 ft³ with 10% waste. That's 1.30 yd³ or 59 × 80 lb bags, and the calculator shows 8 bags per pad if you mix them one at a time.
For round pads, see the next section. If a tube form sits on the pad, add the tube with the sonotube calculator.
Round footings and gazebo footings
A round footing is a short cylinder: π × (diameter in ft ÷ 2)² × depth in ft. Four 24 in round footings, 12 in deep, hold 3.14 ft³ each, 12.57 ft³ in total, or 13.82 ft³ (0.51 yd³, 24 × 80 lb bags) with 10% waste. Enter them in the concrete column calculator with a height of 1 ft and a quantity of 4.
Gazebo and pergola footings are usually a set of identical pads, one per post. Six 24 × 24 × 12 in square pads are 6 × 4 = 24 ft³, or 26.4 ft³ with 10% waste: 0.98 yd³ or 44 × 80 lb bags. Enter length 2 ft, width 24 in, depth 12 in and quantity 6 above.
Trench footings vs formed footings
- Formed footings have boards on both sides. Measure inside the forms and the volume will be close to the calculation.
- Trench-poured footings use the soil as the form. Trenches are almost always dug a little wider and deeper than drawn, so measure the actual trench at several points. Use a higher waste allowance (15% or more) if the walls are ragged.
Small differences add up over a long run. On the 56 ft example, a trench that's 18 in wide instead of 16 in needs 12.5% more concrete. So does one that's 9 in deep instead of 8 in. If your measurements vary, use the larger ones, not the drawing.
Metric measurements
Each box has a unit menu, so you can enter the run in meters and the width and depth in centimeters. A 17 m run of 40 × 20 cm footing is 17 × 0.4 × 0.2 = 1.36 m³, about 1.78 yd³ or 81 × 80 lb bags before waste.
Footing mistakes that cost a second truck
- Counting corners twice, as described above.
- Using the wall thickness instead of the footing width. The footing is usually wider than the wall it carries.
- Forgetting stepped sections. On a slope, footings may step down. Run each level as its own length and depth.
- Ordering exactly. A short pour on a footing leaves a cold joint at the worst possible place. Keep the allowance.
Frequently asked questions
How much concrete for gazebo footings?
Six 24 × 24 × 12 in pads take 24 ft³, or 0.98 yd³ (44 × 80 lb bags) with 10% waste. Change the quantity to match your post count.
How many yards of concrete for a 100 ft footing, 16 × 8?
100 × 1.333 × 0.667 = 88.9 ft³ = 3.29 yd³ before waste, or 3.62 yd³ with 10%.
How much concrete per linear foot of footing?
Width × depth, both in feet. A 16 × 8 in footing holds 1.333 × 0.667 = 0.89 ft³ per foot, which is 0.33 yd³ for every 10 ft.
How do I calculate a pad footing?
Side × side × depth, all in feet. A 24 × 24 × 12 in pad is 2 × 2 × 1 = 4 ft³, or 7 × 80 lb bags.
Does rebar reduce the concrete needed in a footing?
Not noticeably. Two ½ in bars take up about 0.31% of a 16 × 8 in footing. The waste allowance covers far more than that.
Should I add the wall concrete here too?
No. Calculate the wall separately with the wall calculator, then add the two if they're poured together.
Bags or ready-mix for footings?
Two yards is 90 × 80 lb bags before waste. Most footing jobs are ready-mix pours.
Sources
- QUIKRETE Concrete Mix (No. 1101) data sheet: bag yields, and its note to follow local building codes for load-bearing footings. https://www.quikrete.com/pdfs/data_sheet-concrete%20mix%201101.pdf
- SAKRETE High-Strength Concrete Mix technical data sheet: bag yields. https://www.sakrete.com/wp-content/uploads/2024/01/Sakrete-High-Strength-Concrete-Mix-TDS.pdf
- NIST, SI units of length: 1 in = 25.4 mm exactly. https://www.nist.gov/pml/owm/si-units-length
- NIST, U.S. survey foot: 1 ft = 0.3048 m exactly. https://www.nist.gov/pml/us-surveyfoot