Worked example: a 30 ft path from driveway to door
| Width | Volume before waste | With 10% | 80 lb bags |
|---|---|---|---|
| 3 ft | 30 ft³ | 1.22 yd³ | 55 |
| 4 ft | 40 ft³ | 1.63 yd³ | 74 |
At 4 ft: 30 × 4 × (4 ÷ 12) = 40 ft³. With 10% that's 44 ft³ = 1.63 yd³.
Over 1.5 yards, either size is at the point where a ready-mix delivery is worth pricing against 55–74 bags.
Curved and winding paths
- Lay a garden hose along the centerline of the path and mark it.
- Straighten the hose and measure it. That's your length.
- Use the average width.
Length along the centerline × average width is close enough for ordering. Keep the 10% waste allowance, because curved forms are harder to keep straight.
Worked example: a front walk plus a side service walk
QUIKRETE's sidewalk instructions suggest 3 to 4 ft for a front-entrance walk and 2 to 3 ft for a service walk to a side or back door. They also say walks should be at least 4 in thick and slope about ¼ in per foot away from the house.
Take a 24 ft front walk at 3.5 ft wide and an 18 ft side walk at 2.5 ft wide, both 4 in thick:
- Front: 24 × 3.5 × (4 ÷ 12) = 28 ft³. With 10% waste that's 30.8 ft³ = 1.14 yd³, or 52 × 80 lb bags.
- Side: 18 × 2.5 × (4 ÷ 12) = 15 ft³. With 10% waste that's 16.5 ft³ = 0.61 yd³, or 28 × 80 lb bags.
- Together: 43 ft³ before waste, 47.3 ft³ = 1.75 yd³ with 10%. That's 79 × 80 lb bags, or 106 × 60 lb.
Total the cubic feet before you round the bags (79 together, against 52 + 28 = 80 rounded separately). At almost 1.75 yd³, compare a short-load ready-mix price with nearly 80 bags. Enter each run in the calculator and add them, or use the concrete bag calculator with the combined volume.
Paths that meet steps or a slab
Run each section separately: the path here, the stairs and any landing pad on the slab calculator. Then add the totals for one order.
Pour in sections, not in pieces
On a long walk, it's tempting to mix a few bags at a time over a weekend. Plan the pour so each section between control joints or forms is filled in one go. Stopping in the middle of a bay can leave a cold joint, which QUIKRETE's data sheet warns against.
Walkway mistakes
- Measuring the planned width, not the forms. Forms set slightly wide add up quickly over a long run.
- Ignoring slope. On a sloped path, measure the length along the slope, not the horizontal distance on a plan.
- Forgetting the base. Estimate the gravel underneath with the gravel calculator.
Sidewalk, patio, slab or driveway calculator?
- Sidewalk (this page): long, narrow runs where width is the main decision. The tables are per 10 ft of length.
- Patio calculator: a wide area you walk on, usually measured as a rectangle.
- Slab calculator: shed bases, pads and anything with a thickened edge.
- Driveway calculator: anything a car will drive on. Use that page's thickness, not the 4 in walk figure. For a worked two-car example, see yards of concrete for a two-car driveway.
Concrete per 10 ft of walk
No waste is included. Multiply by your length in tens of feet.
| Width | Thickness | Per 10 ft | Cubic yards | 80 lb bags |
|---|---|---|---|---|
| 3 ft | 4 in | 10.00 ft³ | 0.37 | 17 |
| 3 ft | 5 in | 12.50 ft³ | 0.46 | 21 |
| 4 ft | 4 in | 13.33 ft³ | 0.49 | 23 |
| 4 ft | 5 in | 16.67 ft³ | 0.62 | 28 |
| 5 ft | 4 in | 16.67 ft³ | 0.62 | 28 |
| 5 ft | 5 in | 20.83 ft³ | 0.77 | 35 |
A 5 ft walk at 4 in uses the same concrete as a 4 ft walk at 5 in.
Longer walks, 4 ft wide at 4 in
With 10% waste:
| Length | Volume | Cubic yards | 80 lb bags |
|---|---|---|---|
| 20 ft | 29.33 ft³ | 1.09 | 49 |
| 30 ft | 44.00 ft³ | 1.63 | 74 |
| 50 ft | 73.33 ft³ | 2.72 | 123 |
| 100 ft | 146.67 ft³ | 5.43 | 245 |
Past about 50 ft, a walk is well into ready-mix territory. If the truck can't reach the far end, ask about a pump or plan wheelbarrow runs.
Measuring a walk
- Stake both edges and pull string lines. Measure the width between the strings at each end and the middle.
- Measure the length along one string, not on the plan.
- Check the depth below the string every few feet. A dip in the base is extra concrete.
- Count the base separately. SAKRETE's data sheet describes placing several inches of gravel in the excavation before the concrete. That depth is not part of the concrete thickness.
For how deep a gravel base is usually made and how to order it, see how much gravel under a concrete slab.
Frequently asked questions
How much concrete for a 4 ft wide sidewalk?
At 4 in thick, 1.33 ft³ per foot of length. A 30 ft walk is 40 ft³ = 1.48 yd³ before waste.
Is 3 ft wide enough?
It's a design choice. The calculator shows the difference in concrete: 25% less than 4 ft.
How many bags of concrete for a 10 ft sidewalk?
At 4 ft wide and 4 in thick, 13.33 ft³: 23 × 80 lb bags before waste.
How many yards of concrete for a 100 ft sidewalk?
At 4 ft wide and 4 in thick, 133.33 ft³ = 4.94 yd³ before waste, or 5.43 yd³ with 10%.
Sources
- QUIKRETE Concrete Mix (No. 1101) data sheet: yields and the partial-fill warning. https://www.quikrete.com/pdfs/data_sheet-concrete%20mix%201101.pdf
- SAKRETE High-Strength Concrete Mix technical data sheet: bag yields. https://www.sakrete.com/wp-content/uploads/2024/01/Sakrete-High-Strength-Concrete-Mix-TDS.pdf
- QUIKRETE, "Concrete Sidewalks and Small Slabs" project instructions: walk widths, 4 in minimum thickness, ¼ in per ft slope. https://www.quikrete.com/pdfs/projects/concretesidewalksandsmallslabs.pdf