MyProjectCalcs

How Many Yards of Concrete for a 2-Car Driveway?

By Vinod Kondeti · Published

A two-car driveway pad 24 ft wide and 20 ft long holds 160 cubic feet of concrete at 4 inches thick, which is 5.93 cubic yards. At 5 inches it’s 7.41 yd³, and at 6 inches 8.89 yd³. Add a 10% allowance for an uneven base and spillage and you would order about 6.52, 8.15 or 9.78 yd³.

Which of those you need depends on the thickness, and the thickness depends on what will drive on it. The rest of this post covers the math, a size table, how to choose between 4, 5 and 6 inches, and what to sort out with the ready-mix plant before the truck arrives. To run your own measurements, use the driveway concrete calculator.

The math for a 24 × 20 ft driveway

Concrete is ordered by volume, so multiply length × width × thickness with every measurement in feet, then divide by 27 to get cubic yards.

  1. Area: 24 ft × 20 ft = 480 ft².
  2. Volume at 4 in: 480 × (4 ÷ 12) = 160 ft³.
  3. Cubic yards: 160 ÷ 27 = 5.93 yd³ (about 4.53 m³).
  4. With 10% extra: 160 × 1.10 = 176 ft³, or 6.52 yd³.

On this pad, every extra inch of thickness adds 40 ft³, which is 1.48 yd³ (1.63 yd³ with the allowance). That is why the thickness decision matters more than small differences in length or width.

QUIKRETE’s driveway guide says a driveway for a two-car garage is usually about 24 ft wide, which is why the worked example uses that width. Measure your own forms rather than the old paving or the lot plan, since the new pour may not match either.

Cubic yards for common 2-car driveway sizes

Each row shows cubic yards before waste, then with 10% extra in brackets. All numbers come from the same length × width × thickness formula the slab calculator uses.

Size (ft) Area 4 in 5 in 6 in
18 × 20 360 ft² 4.44 (4.89) 5.56 (6.11) 6.67 (7.33)
20 × 20 400 ft² 4.94 (5.43) 6.17 (6.79) 7.41 (8.15)
24 × 20 480 ft² 5.93 (6.52) 7.41 (8.15) 8.89 (9.78)
24 × 24 576 ft² 7.11 (7.82) 8.89 (9.78) 10.67 (11.73)

For a quick estimate on any size, 100 ft² of driveway takes 1.23 yd³ at 4 inches, 1.54 yd³ at 5 inches and 1.85 yd³ at 6 inches, before waste. A long drive adds up fast. A 24 × 40 ft drive at 5 inches is 14.81 yd³, or 16.30 yd³ with 10% extra.

If your driveway narrows to a single lane, flares at the street or has a wider pad in front of the garage, split it into rectangles and triangles, work out each area with the square footage calculator, and add them up before multiplying by the thickness.

4, 5 or 6 inches thick?

QUIKRETE’s driveway guide says thickness depends on the weight of the vehicles. For passenger cars only, 4 inches is sufficient. If trucks and other heavy vehicles will use the driveway, it recommends 5 or 6 inches. The Michigan Concrete Association’s driveway and sidewalk guidelines set a 4 inch minimum and raise it to 5 inches when traffic will include delivery vehicles.

In practice that means:

  • 4 in: cars and light SUVs only.
  • 5 in: delivery vans, pickups, or anything heavier that will use the drive now and then.
  • 6 in: regular truck traffic, or whenever your plans or contractor call for it.

Your local building department, HOA or contractor may set their own minimum, and the part of the driveway between the street and the sidewalk is usually controlled by the town, according to QUIKRETE’s guide. Check those rules first, then size the order.

Thickness is only part of the design. Reinforcement, joint spacing and a thickened edge are settled by your plans or contractor. If the plan thickens the edges, add that strip separately with the footing calculator.

Ordering ready-mix: rounding, trucks and short loads

Round the order up

One ready-mix supplier’s ordering guide (R&R Ready Mix) tells customers to add 10% for an uneven subgrade and spillage, then round up to the nearest quarter yard. For the 24 × 20 pad that turns 6.52 yd³ into 6.75 yd³ at 4 inches, 8.15 into 8.25 yd³ at 5 inches, and 9.78 into 10 yd³ at 6 inches. The same guide notes that it’s easier to cancel a truck than to add one, so ask your plant how it handles a top-up load if you run short.

How much fits on one truck

The National Ready Mixed Concrete Association (NRMCA) says that, because of weight laws, the typical truck mixer is a 9 to 11 yd³ unit. With the allowance, every size in the table comes in under 9 yd³ at 4 inches, and all but the 24 × 24 do at 5 inches, so most two-car pads fit on one load. A 24 × 24 pad at 6 inches (11.73 yd³ with the allowance) or the 24 × 40 ft drive above (16.30 yd³) will likely need two trucks, so ask the plant how it will space them.

Short-load fees and unloading time

Small orders can cost more per yard. R&R Ready Mix, for example, adds a partial-load charge to every load under 6 yd³. That would cover an 18 × 20 pad at 4 inches (4.89 yd³ with 10% extra). Other plants set different thresholds, and the NRMCA and ASCC checklist for ordering ready-mix lists short-load charges among the things to agree with your supplier up front.

Unloading time is billed too. The same supplier allows 6 minutes per cubic yard and charges for each minute over. At that rate, 8.25 yd³ gets about 50 minutes, so have your forms, base, tools and crew ready before the truck arrives. That matters even more if the concrete has to go in by wheelbarrow.

Why not bags?

SAKRETE says it takes 45 bags of 80 lb mix to make one cubic yard. The 24 × 20 pad at 4 inches with 10% extra would take 294 × 80 lb bags, about 23,500 lb of dry mix. QUIKRETE’s data sheet says to allow 1 ft³ of mixer capacity per 80 lb bag and to fill forms to full depth, because partial-depth fills can leave cold joints. Bags make sense for small pads. For a sense of that scale, see how many bags of concrete for a 10x10 slab. A full driveway is a truck job. The concrete bag calculator turns any yardage into bag counts if you want to compare.

The base under the driveway

The concrete sits on a compacted base, and that is a separate order. The Michigan Concrete Association guidelines call for removing unstable material to at least 6 inches, replacing it with crushed stone, gravel or sand compacted to 95%, and using a sub-base of at least 4 inches after compaction. They also say a driveway should never be built on a frozen subgrade or sub-base.

For the 24 × 20 pad, 4 inches of base is 160 ft³, or 5.93 yd³ (6.52 yd³ with the gravel calculator’s default 10% extra). If you extend the base 6 inches past each edge, as QUIKRETE’s patio instructions call for under a slab, the footprint becomes 25 × 21 ft and the base is 6.48 yd³ (7.13 yd³ with 10%). Gravel is sold by weight as well as volume, so ask your supplier how much its product weighs per cubic yard. The gravel section of how much concrete for a 10x8 shed base walks through the same steps on a smaller pad.

Frequently asked questions

How many yards of concrete for a 2-car driveway?

For a 24 × 20 ft pad, 5.93 yd³ at 4 inches, 7.41 yd³ at 5 inches or 8.89 yd³ at 6 inches, before waste. With 10% extra, that’s 6.52, 8.15 or 9.78 yd³.

How many yards for a 20x20 driveway?

4.94 yd³ at 4 inches, 6.17 at 5 inches and 7.41 at 6 inches, before waste. With 10% extra, that’s 5.43, 6.79 and 8.15 yd³.

Is 4 inches thick enough for a driveway?

For passenger cars only, QUIKRETE says 4 inches is sufficient. If delivery vehicles or trucks will use it, the Michigan Concrete Association guidelines and QUIKRETE call for 5 inches or more. Follow your local rules and plans if they say otherwise.

Will a 2-car driveway fit on one concrete truck?

Usually, if the pad is around 24 × 20 ft and 4 or 5 inches thick. NRMCA says typical truck mixers carry 9 to 11 yd³, so bigger or thicker pours may need a second load. Ask your plant.

How long before I can drive on a new driveway?

The Michigan Concrete Association guidelines say a driveway can open to traffic after 7 days of curing, or sooner if testing shows it has reached 2,500 psi. Check with your installer or supplier for your mix and weather.

Sources

Tags: concrete, driveways, ready-mix